ROAD CLOSURES: Manchester Town Hall Development Project

29th Sep 2021

Town Hall Project – Planned Road Closures and Diversions

27th September 2021 – 26th March 2023

NB. no works will take place in between 30/09/2021 and 06/10/2021 to enable the set-up of the Conservative Party Conference.

The effect of the Order is to prohibit traffic on ALBERT SQUARE, MOUNT STREET, SOUTHMILL STREET, BOOTLE STREET, CENTRAL STREET, LLOYD STREET, COUNTY STREET.

Phase 3 to be completed by 24-10-2021

MAP

Schedule 1 – Phase 1 (as shown on map in black)

  • Southmill Street from Central Street to Lloyd Street
  • Bootle Street from Southmill Street to Mount Street
  • Jacksons Row from Deansgate to Southmill Street
  • Lloyd Street from Deansgate to Southmill Street

Diversion: Southmill Street, Jacksons Row, Deansgate, Peter Street, Mount Street and Southmill Street, Jacksons Row, Deansgate, Peter Street, Marron Place.

Schedule 2 – Phase 2 (as shown on map in red)

  • Central Street for its Full Length
  • Bootle Street from Southmill Street to Mount Street
  • Bootle Street from Southmill Street to Marron Place
  • Southmill Street from Peter Street to Jacksons Row

Diversion: Peter Street, Southmill Street, Lloyd Street.

Schedule 3 – Phase 3 (as shown on map in blue)

  • Central Street for its Full Length
  • Bootle Street from Southmill Street to Mount Street
  • Mount Street from Peter Street to Lloyd Street

Diversion: Deansgate, Peter Street, Mount Street.

Schedule 4 – from completion of works to start of permanent TRO (as shown on map in green)

  • Mount Street from 77 metres north of its junction with Peter Street to its junction with Lloyd Street
  • County Street for its Full Length
  • Albert Square from Mount Street to Tasle Alley